ocan_dispatch: Verification Report¶
1. Test results¶
Run with GHDL 6.0.0 (mcode), VUnit 5.0.0.dev7 and UVVM 2026.02.14: python run.py "*ocan_dispatch*".
| Testbench | Test cases | Runs (test case and configuration) | Passed |
|---|---|---|---|
ocan_dispatch_tb |
16 | 25 | 25 |
ocan_dispatch_net_tb |
2 | 2 | 2 |
The configurations are those of section 2 of the verification plan. In the direct testbench
the transmit side of the link is a model of the specification of ocan_link and of the completion invariant of
the architecture (section 5.1): LinkTx_Ready is '1' while no frame is pending and the link neither switches nor
is stopped, and '0' from the cycle after the take to the cycle of the completion event; a checker confirms in every
test that every completion event of a source belongs to a taken request of that source. The network testbench runs
ocan_dispatch with ocan_link on the CAN network model of tb/.
QuestaSim (Questa Pro Microchip Edition 2024.3): the same tests pass in the regression without code coverage
(python run.py --questa -p 1) and with it (python run.py --questa --coverage -p 1); the coverage is in
docs/coverage.md.
2. Measured values¶
| Item | Value |
|---|---|
| Link event to a protocol output or a per-bus event | 1 clock cycle (every check of the direct testbench) |
Held NMT message to RxNmt_Valid |
1 clock cycle after the active bus changed to its bus (TC-DS-05) |
| Completion event of a source to the next grant of the same source | 1 clock cycle; no Ready in the cycle of Done or Aborted (TC-DS-15, sources 0, 5 and 6) |
| Smallest distance of two events to one block, back-to-back frames at 1 Mbit/s | NMT 175 µs, PDO block 49 µs, time block 50 µs, SDO 196 µs; none below 46 bit times (TC-DS-06) |
| Cyclic transmit order with all seven sources pending | TPDO1, TPDO2, TPDO3, TPDO4, Local Time PDO, SDO reply, NMT error control (TC-DS-09) |
| Transmit wait, random requests | 300 frames, no request waited for more than one frame of each other source (TC-DS-09) |
Lost completion: LinkTx_Ready again without a completion event, to Aborted of the owner |
1 clock cycle; the requests of three sources are sent afterwards (TC-DS-16) |
| Frames back to back, completion 1, 2 and 3 cycles after the take | No Aborted, every frame Done once, one frame on the link per Done, for all seven sources (TC-DS-17) |
Stop of the controller of the active bus between the grant and the take, to Aborted of the owner |
1 clock cycle; no grant while stopped; the waiting request is sent after the re-enable, the withdrawn frame never (TC-DS-18) |
| Bus switch of 20 cycles from a grant on | The frame waits in Send_s and is sent, no abort (TC-DS-18) |
| Transmit wait under load, heartbeat every 1 ms, contention and error frames on the bus | 42 frames passed to the link, the bound held for every frame; the longest wait of a heartbeat for the link was 2.48 ms, caused by lost arbitrations against model nodes, not by other sources of the dispatch (TC-DS-12) |
3. Generic ranges¶
| Generic | Declared range | Simulated | Synthesised (lint/synth_check.py) |
|---|---|---|---|
NumRpdo_g |
0 to 4 | 0, 1, 2, 3, 4 | 0, 1, 2, 3, 4 |
NumTpdo_g |
0 to 4 | 0, 1, 2, 3, 4 | 0, 1, 2, 3, 4 |
TimePdos_g |
true, false | both | both |
SdoServer_g |
true, false | both | both |
4. Negative tests and mutations¶
Every checker of the plan has a negative test (verification plan, section 5); TC-DS-02 sends a frame that nearly
matches for every receive rule. In addition, 23 deliberate faults of the RTL were each simulated with the tests that
must detect them, and every one made a test fail (the guard of DS-TX-03 also in the network bench of
ocan_nmt, TC-NM-21):
| Fault | Detected by |
|---|---|
| No DLC check of the NMT message | TC-DS-02 |
| No addressing check of the NMT message | TC-DS-02 |
| Extended frames accepted | TC-DS-02 |
| Remote frames accepted | TC-DS-02 |
| Free COB-IDs usable | TC-DS-02, TC-DS-11 |
| COB-ID copies not compared | TC-DS-02, TC-DS-13 |
| COB-ID mismatch event in every cycle of a mismatch | TC-DS-13 |
| Bus A always taken as the active bus | TC-DS-01, TC-DS-04 |
| NMT message of the inactive bus not held | TC-DS-05 |
| Held NMT message never passed | TC-DS-05 |
| SDO requests passed without the SDO enable | TC-DS-03 |
| Fixed priority instead of the round robin | TC-DS-09 |
| No reject path | TC-DS-10 |
No withdraw in Send_s |
TC-DS-10 |
No abort request in Wait_s |
TC-DS-10 |
| SDO identifier computed with 7 bits | TC-DS-01 |
| Grant in the cycle of the own completion event | TC-DS-15 |
No completion as aborted at LinkTx_Ready in Wait_s (DS-TX-07) |
TC-DS-16 |
Completion as aborted at LinkTx_Ready also in the cycle of a completion event |
TC-DS-17, TC-DS-08 |
| A grant while the link cannot take a frame (DS-TX-08) | TC-DS-18 |
Ready to a source without the link ready |
TC-DS-18 |
No withdraw in Send_s when the link is stopped |
TC-DS-18 |
Withdraw in Send_s also during a bus switch |
TC-DS-18, TC-DS-10 |
The fault of the SDO identifier was a real error of the first version of the RTL, found by TC-DS-01 before the mutation
check. All 23 faults ran on the RTL of the bounded transmit waits; the change moved the text of two faults of the first
check (the fixed priority, now at Out_Ready of the arbiter, and the withdraw in Send_s), which were simulated again
as the same faults at their new places.
5. Summary¶
All 18 test cases pass in all 27 runs; every requirement of the specification is covered by the verification plan. VSG reports no errors and no warnings, and the GHDL synthesis of every configuration has no inferred latch.